The Palm River Public Utility Renewal project is part of Collier County’s PUR initiative, replacing aging water, wastewater, and stormwater systems in Basin 305. The Palm River Public Utility Renewal Project is a multi-year initiative to upgrade aging infrastructure in Basin 103, which includes the Palm River Estates neighborhood. With over 10 miles of roadway and approximately 1,500 properties, this primarily residential area is experiencing frequent water main breaks, service line failures, and localized flooding.
The project replaces outdated utility systems and improve stormwater management to enhance service reliability, environmental protection, and neighborhood walkability.
Scope of Work
Replacement of water, wastewater, and stormwater systems
Installation of PVC pipe to replace aging clay sewer laterals
Rehabilitation of stormwater collection and treatment systems within the public right-of-way
Addition of sidewalks and roadway improvements for safer pedestrian access
Note: Some work may require access to private property. Residents will be contacted for permission as needed.
The Palm River Public Utility Renewal project is part of Collier County’s PUR initiative, replacing aging water, wastewater, and stormwater systems in Basin 305. The Palm River Public Utility Renewal Project is a multi-year initiative to upgrade aging infrastructure in Basin 103, which includes the Palm River Estates neighborhood. With over 10 miles of roadway and approximately 1,500 properties, this primarily residential area is experiencing frequent water main breaks, service line failures, and localized flooding.
The project replaces outdated utility systems and improve stormwater management to enhance service reliability, environmental protection, and neighborhood walkability.
Scope of Work
Replacement of water, wastewater, and stormwater systems
Installation of PVC pipe to replace aging clay sewer laterals
Rehabilitation of stormwater collection and treatment systems within the public right-of-way
Addition of sidewalks and roadway improvements for safer pedestrian access
Note: Some work may require access to private property. Residents will be contacted for permission as needed.
Collier County Public Utilities is interested in understanding how the local community feels about the utility construction projects. No names or other personally identifiable information is collected in this survey. We greatly appreciate you taking the time to share your thoughts.
Share Community Survey on FacebookShare Community Survey on TwitterShare Community Survey on LinkedinEmail Community Survey link
Page last updated: 21 Oct 2025, 08:26 AM
Progress
Areas 1 & 2
Palm River Public Utilities Renewal has finished this stage
These areas included infrastructure upgrades along Cypress Way East, Palm River Boulevard, Golfview Drive, Pompano Drive, and Eastwood Drive. The project replaced aging water, sewer, and stormwater systems, rehabilitated two wastewater pump stations, and added a new sidewalk along Cypress Way East.
New PVC water mains, fire hydrants, and water services installed
Sewer and stormwater systems fully upgraded
Pump stations rehabilitated
Roads and driveways restored
Final walkthrough and punch list completed
Area 4 – In Construction
Palm River Public Utilities Renewal is currently at this stage
Located in Cocohatchee River Estates on the west side of Palm River, Area 4 includes 24 single-family homes currently served by septic systems. The project is installing a new PVC water main and converting properties to a centralized sewer system via horizontal directional drilling.
Water main replacement underway
Septic systems being abandoned
New force main sewer system installation in progress
Driveways and roads will be fully restored upon completion
Area 3,5 & 6 - In Design
this is an upcoming stage for Palm River Public Utilities Renewal
These areas are part of the next phase of improvements within Palm River. The project will continue replacing aging water, sewer, and stormwater infrastructure and extend the benefits of the PUR program to additional residential streets.
Status: 📐 80% Design Phase
Engineering and planning in progress
Construction timeline to be announced upon design completion
Community Benefits
Reliable water service for current and future residents
Infrastructure to support future distribution mains
Increased fire protection through new hydrants
Improved system performance and long-term sustainability